Nile Dam Talks Delayed for ‘Consultations’

Construction workers work at night at the Grand Ethiopian Renaissance Dam (GERD), near Guba in Ethiopia, on December 26, 2019. – The Grand Ethiopian Renaissance Dam, a 145-metre-high, 1.8-kilometre-long concrete colossus is set to become the largest hydropower plant in Africa.
Across Ethiopia, poor farmers and rich businessmen alike eagerly await the more than 6,000 megawatts of electricity officials say it will ultimately provide.
Yet as thousands of workers toil day and night to finish the project, Ethiopian negotiators remain locked in talks over how the dam will affect downstream neighbours, principally Egypt. (Photo by EDUARDO SOTERAS / AFP)

Khartoum, Sudan, August 12, 2020//-Sudan on Monday said that negotiations over Ethiopia’s massive and controversial dam construction on the Blue Nile have been postponed for a week.

Talks between Ethiopia, Egypt and Sudan were suspended last week after Addis Ababa insisted on linking them to renegotiating a deal on sharing the waters of the Blue Nile.

“A meeting at the level of ministers of the three countries took place on Monday, during which Sudan asked to postpone the next meeting for one week for internal consultations,” Sudan’s water ministry said in a statement.

Egypt and Sudan view the Grand Ethiopian Renaissance Dam (GERD) dam as a threat to vital water supplies, while Ethiopia considers it crucial for its electrification and development.

South Africa, which holds the presidency of the African Union and is mediating negotiations, has urged the countries to “remain involved” in the talks.

AFP

Leave a Reply

*